Wednesday, 20 December 2017 22:13

Hydro Tasmania probe finds cause of 2015 Basslink cable failure

By

The cause of the December 2015 failure of the Basslink cable has finally been identified, with two experts saying it happened because Basslink Pty Ltd exceeded its design limit.

A statement from Hydro Tasmania said that expert reports had concluded that BPL operated the cable in a way that caused degradation with issues related to heating and cooling under operational stress the probable cause of the failure.

These experts had recommended that a short-term export limit of 500MW be observed while Basslink considered and responded to the new information. They were confident that the cable could operate safely at 500MW.

At one stage, in December last year, Basslink had described the outage as an "act of God".

The experts concluded that the cable could safely and reliably operate above 500MW in future, if BPL adopts a new control system and extends the cable’s “rest period” between polarity reversals (between export/import and vice versa) from two minutes to five minutes.

Hydro Tasmania chief executive Steve Davy (below, right) said the findings vindicated Hydro Tasmania’s decision to conduct its own investigation.

“We’re confident this expert investigation solves the mystery of the Basslink failure for all Tasmanians,” he said.

steve davy vert“BPL believed its cable could safely and reliably operate at 630MW for extended periods without overheating the copper and insulation and causing an unreasonable likelihood of failure. Unfortunately, they were wrong. The expert reports note that the cable, as designed and constructed, cannot meet the minimum operating requirements.

“We received the expert reports in recent days, and have submitted them to BPL. The Basslink cable is the sole responsibility of its owner. It’s now incumbent on BPL to consider the reports and take the necessary steps to improve its cable to the standard and specifications promised.

“The expert investigation identifies the probable cause of the cable failure. But most importantly, it also identifies both interim and long-term solutions to ensure Basslink can operate as reliably as it was supposed to in future."

The investigation was carried out by a power cable failure expert and a thermal modelling expert from international engineering consultancy DNV GL, which is recognised as the global leader in this field.

The experts concluded that the failure was probably caused by electrical energy discharge within the cable as a result of polarity reversal and cooling shortly before the 20 December 2015 incident.

Recommendations include a short-term (and interim) measure of limiting the capacity of Basslink to 500MW (the continuous rating of the cable). This would mean that maximum export capacity of Basslink of 630MW would not be available for some time. This step would mitigate the risk of temperature design limits being exceeded.


Subscribe to ITWIRE UPDATE Newsletter here

Active Vs. Passive DWDM Solutions

An active approach to your growing optical transport network & connectivity needs.

Building dark fibre network infrastructure using WDM technology used to be considered a complex challenge that only carriers have the means to implement.

This has led many enterprises to build passive networks, which are inferior in quality and ultimately limit their future growth.

Why are passive solutions considered inferior? And what makes active solutions great?

Read more about these two solutions, and how PacketLight fits into all this.

CLICK HERE!

WEBINAR INVITE 8th & 10th September: 5G Performing At The Edge

Don't miss the only 5G and edge performance-focused event in the industry!

Edge computing will play a critical part within digital transformation initiatives across every industry sector. It promises operational speed and efficiency, improved customer service, and reduced operational costs.

This coupled with the new capabilities 5G brings opens up huge opportunities for both network operators and enterprise organisations.

But these technologies will only reach their full potential with assured delivery and performance – with a trust model in place.

With this in mind, we are pleased to announce a two-part digital event, sponsored by Accedian, on the 8th & 10th of September titled 5G: Performing at the Edge.

REGISTER HERE!

BACK TO HOME PAGE
Sam Varghese

website statistics

Sam Varghese has been writing for iTWire since 2006, a year after the site came into existence. For nearly a decade thereafter, he wrote mostly about free and open source software, based on his own use of this genre of software. Since May 2016, he has been writing across many areas of technology. He has been a journalist for nearly 40 years in India (Indian Express and Deccan Herald), the UAE (Khaleej Times) and Australia (Daily Commercial News (now defunct) and The Age). His personal blog is titled Irregular Expression.

Share News tips for the iTWire Journalists? Your tip will be anonymous

WEBINARS ONLINE & DEMAND

GUEST ARTICLES

VENDOR NEWS

Guest Opinion

Guest Interviews

Guest Reviews

Guest Research

Guest Research & Case Studies

Channel News

Comments