Basslink has denied claims by the Tasmanian Government that it had breached warranties about the design and construction of the Basslink Interconnector and reiterated that the failure was a force majeure event.

Published in Telecoms & NBN

Basslink chief executive Malcolm Eccles has dismissed Hydro Tasmania's claim that it had found the reason behind the Basslink cable failure in 2015, saying that the expert reports cited as proof merely outlined one possible cause of the outage.

Published in Telecoms & NBN

The cause of the December 2015 failure of the Basslink cable has finally been identified, with two experts saying it happened because Basslink Pty Ltd exceeded its design limit.

Published in Telecoms & NBN